Posted on 23 October, 2018
The new floor was got finished today. This needs to harden, therefore no further updates the coming days.
Here you can find the latest news or announcements of Royal Zoute Golf Club.
Posted on 23 October, 2018
The new floor was got finished today. This needs to harden, therefore no further updates the coming days.
Posted on 21 October, 2018
In preparation of constructions works which will commence shortly. The terrain got cleared in the area of the new teaching cabins.
Posted on 0 October, 2018
The new Starter cabin is rain and weatherproof.
Except for the roof, which needs some further finishing touches, the outside look of the cabin is finished.
The works inside are on schedule, the new insulated walls, preliminary electricity and heating related work is finished. Next week they will pour the concrete for the floor.
Posted on 08 October, 2018
The coming month's multiple big renovation works will commence.
Hereby the schedule of the works:
-October-November: Works on the Starter Cabine.
-10 October - 24 October: Preparations for the renovation Roof Clubhouse
-24 Ocotober - March 2019: Renovation Roof Clubhouse + renovation Changing rooms and showers
-November 2018 - January 2019: Construction Teaching centre.
We will do our best to minimise the inconvenience for all members and players.